Impact of client relationship on project delay: Moderating role of project governance

Iqra Ayaz, Muhammad Faizan Khan, Muhammad Tanveer, Mansour Mrabet, Syed Hussain Mustafa Gillani

Article ID: 6397
Vol 8, Issue 10, 2024

VIEWS - 31 (Abstract) 4 (PDF)

Abstract


The projects of the IT industry are considered successful when they are completed within the timeline, budget, and client satisfaction on a specific project. Although client relationship is not given much importance in the delay of a project, through several studies it has been seen that the project is delayed in the IT industry due to a lack of awareness about the project to the client. The objective of this study is to inspect the impact of client relationships on project delay. Drawing on stakeholder theory and agency theory, this study investigates how client relationship influences project delay through project awareness and the role of project governance as moderator. A deductive approach of reasoning was used to test the hypotheses formulated under the current research work and proceed by using the quantitative method. This study employed a cross-sectional research design, where data was collected at a specific point in time through a survey strategy. Data was collected from the sample of 288 respondents from the IT companies of Rawalpindi and Islamabad. The data was collected using a convenience sampling technique. The demographics of the respondents were analyzed through the IBM-SPSS software program. The assumptions and the reliability of the model were also tested in SPSS. In this study, it was discovered that effective management of client relationships significantly reduces project delays, with project awareness being a crucial factor in this mitigation process. The results revealed that client relationship was negatively associated with project delay and project awareness. Whereas this linkage was mediated by project awareness. This study concludes that adequate project awareness and fruitful project governance reduce project delays and lead to positive client relationships.


Keywords


client relationship; management; project delay; project awareness and project governance

Full Text:

PDF


References


Abulhakim, N., & Adeleke, A. Q. (2019). The factors contributing to accident occurrence on Malaysia building projects through partial least square structural equation modelling. Social Science and Humanities Journal, 4(1), 1096–1106.

Adeleke, A. Q., Bahaudin, A. Y., Kamaruddeen, A. M., et al. (2019). An Empirical Analysis of Organizational External Factors on Construction Risk Management. International Journal of Supply Chain Management (IJSCM), 8(1), 932–94.

Amjad, S. (2018). Impact of project control on project success with mediating role of project governance and moderating role of project leadership [PhD thesis]. Capital University.

Ballesteros-Sánchez, L., Ortiz-Marcos, I., & Rodríguez-Rivero, R. (2019). The Impact of Executive Coaching on Project Managers’ Personal Competencies. Project Management Journal, 50(3), 306–321. https://doi.org/10.1177/8756972819832191

Chung, R. M., Adeleke, A. Q., & Ajibike, W. A. (2020). Client Delay Factors Affecting Building Project Performance Among Kuantan Malaysian Construction Industry: Through Partial Least Square Structural Equation Modeling. Journal of Business Management and Economic Research, 4(1), 38–55. https://doi.org/10.29226/tr1001.2020.182

De Oliveira, G. F., & Rabechini Jr, R. (2019). Stakeholder management influence on trust in a project: A quantitative study. International Journal of Project Management, 37(1), 131–144. https://doi.org/10.1016/j.ijproman.2018.11.001

Denicol, J., Davies, A., & Krystallis, I. (2020). What Are the Causes and Cures of Poor Megaproject Performance? A Systematic Literature Review and Research Agenda. Project Management Journal, 51(3), 328–345. https://doi.org/10.1177/8756972819896113

Derakhshan, R., Turner, R., & Mancini, M. (2019). Project governance and stakeholders: a literature review. International Journal of Project Management, 37(1), 98–116. https://doi.org/10.1016/j.ijproman.2018.10.007

Gebrehiwet, T., & Luo, H. (2017). Analysis of delay impact on construction project based on RII and correlation coefficient: Empirical study. Procedia engineering, 196, 366-374.

Ibraigheeth, M. A., & Fadzli, S. A. (2019). Fuzzy Logic Driven Expert System for the Assessment of Software Projects Risk. International Journal of Advanced Computer Science and Applications, 10(2)

Irfan, M., Khan, S. Z., Hassan, N., et al. (2021). Role of Project Planning and Project Manager Competencies on Public Sector Project Success. Sustainability, 13(3), 1421. https://doi.org/10.3390/su13031421

Keers, B. B. M., & van Fenema, P. C. (2018). Managing risks in public-private partnership formation projects. International Journal of Project Management, 36(6), 861–875. https://doi.org/10.1016/j.ijproman.2018.05.001

Liu, M., Xu, C., Jin, H., et al. (2024). One-2-3-45: Any single image to 3d mesh in 45 seconds without per-shape optimization. Advances in Neural Information Processing Systems, 36.

Larsen, K. R., & Bong, C. H. (2016). A tool for addressing construct identity in literature reviews and meta-analyses. Mis Quarterly, 40(3), 529-552.

Levin, E., Quach, T. N., & Thaichon, P. (2018). Enhancing client-agency relationship quality in the advertising industry–an application of project management. Journal of Business & Industrial Marketing, 34(2), 463-473.

Lechler, T. G., Edington, B. H., & Gao, T. (2012). Challenging classic project management: Turning project uncertainties into business opportunities. Project Management Journal, 43(6), 59-69.

Maruping, L. M., Daniel, S. L., & Cataldo, M. (2019). Developer centrality and the impact of value congruence and incongruence on commitment and code contribution activity in open source software communities. MIS Quarterly, 43(3), 951-976.

Mainga, W. (2017). Examining project learning, project management competencies, and project efficiency in project-based firms (PBFs). International Journal of Managing Projects in Business, 10(3), 454–504. https://doi.org/10.1108/ijmpb-04-2016-0035

Mahmood, H., & Tanveer, M. (2024). Examining the Role of Women’s Labor Participation in CO2 Emissions in Saudi Arabia. International Journal of Energy Economics and Policy, 14(3), 102–108. https://doi.org/10.32479/ijeep.15740

Meng, X., & Boyd, P. (2017). The role of the project manager in relationship management. International Journal of Project Management, 35(5), 717–728. https://doi.org/10.1016/j.ijproman.2017.03.001

Mirza, E., & Ehsan, N. (2017). Quantification of Project Execution Complexity and its Effect on Performance of Infrastructure Development Projects. Engineering Management Journal, 29(2), 108–123. https://doi.org/10.1080/10429247.2017.1309632

Ojelabi, R., Oyeyipo, O., Afolabi, A., & Amusan, L. (2018). Presence of social client relationship management within the Nigerian Construction Industry. Buildings, 8(4), 60.

Osei-Kyei, R., Chan, A. P. C., Javed, A. A., et al. (2017). Critical success criteria for public-private partnership projects: international experts’ opinion. International Journal of Strategic Property Management, 21(1), 87–100. https://doi.org/10.3846/1648715x.2016.1246388

Riazi, S. R. M., Loh, Y. S., Said, I., et al. (2018). The use of supply chain management to overcome low labour productivity issues in the Tenth Malaysia Plan public sector projects. Malaysian Construction Research Journal, 3(1), 178-191.

Rose, J., & Schlichter, B. R. (2012). Decoupling, re-engaging: managing trust relationships in implementation projects. Information Systems Journal, 23(1), 5–33. https://doi.org/10.1111/j.1365-2575.2011.00392.x

Saleem, Y., Crespi, N., Rehmani, M. H., & Copeland, R. (2019). Internet of things-aided smart grid: technologies, architectures, applications, prototypes, and future research directions. Ieee Access, 7, 62962-63003.

Salykova, L. & Abylova, V. (2019). Critical success factors in project management. 1, 2. PM World Journal, 8, 1-13

Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007

Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O. (2020). Causes of delay in the global construction industry: A meta analytical review. International Journal of Construction Management, 22(8), 1395–1407. https://doi.org/10.1080/15623599.2020.1716132

Shah, A., Zhang, Y., Tanveer, M., et al. (2022). Effect of Product Assortment, Internet of Things, Order Fulfillment, Green on Purchase Intention Through the Mediating Role of Shopping Assistance. Journal of Advanced Manufacturing Systems, 22(01), 123–147. https://doi.org/10.1142/s0219686723500075

Shakeri, H., & Khalilzadeh, M. (2020). Analysis of factors affecting project communications with a hybrid DEMATEL-ISM approach (A case study in Iran). Heliyon, 6(8), e04430. https://doi.org/10.1016/j.heliyon.2020.e04430

Shenhar, A., & Dvir, D. (2007). Reinventing Project Management: The Diamond Approach to Successful Growth and Innovation. Boston: Harvard Business School.

Silva, K., (2018). Soft Skills Influence in Project Managers in the Cloud Space [Marster’s thesis]. Harrisburg University.

Tereso, A., Ribeiro, P., Fernandes, G., Loureiro, I., & Ferreira, M. (2019). Project management practices in private organizations. Project Management Journal, 50(1), 6-22.

Tanveer, S. (2019). Impact of Project Planning on Project Delay with the Mediating Role of Project Awareness and Moderating Role of Project Governance 9(1), 88-98.

Tanveer, M. (2022). Supply Chain and Logistics Operations Management Under the Era of Advanced Technology. Integrating Blockchain Technology into the Circular Economy. IGI Global, 126–136. https://doi.org/10.4018/978-1-7998-7642-7.ch008

Uribe, D. F., Ortiz-Marcos, I., & Uruburu, Á. (2018). What is Going on with Stakeholder Theory in Project Management Literature? A Symbiotic Relationship for Sustainability. Sustainability, 10(4), 1300. https://doi.org/10.3390/su10041300

Verenych, O., Sharovara, O., Dorosh, M., et al. (2019). Awareness Management of Stakeholders During Project Implementation on the Base of the Markov Chain. In: Proceedings of the 2019 10th IEEE International Conference on Intelligent Data Acquisition and Advanced Computing Systems: Technology and Applications (IDAACS). https://doi.org/10.1109/idaacs.2019.8924375

Woźniak, P. W., Karolus, J., Lang, F., et al. (2021). Creepy technology: what is it and how do you measure it? In: Proceedings of the 2021 CHI conference on human factors in computing systems. pp. 1-13.

Zaman, U., Abbasi, S., Nawaz, S., & Siddique, M. S. (2020). Linking sustainability management and success in construction projects: Moderating influence of high-performance work systems. Pakistan Journal of Commerce and Social Sciences (PJCSS), 14(3), 661–684.




DOI: https://doi.org/10.24294/jipd.v8i10.6397

Refbacks

  • There are currently no refbacks.


Copyright (c) 2024 Iqra Ayaz, Muhammad Faizan Khan, Muhammad Tanveer, Mansour Mrabet, Syed Hussain Mustafa Gillani

License URL: https://creativecommons.org/licenses/by/4.0/

This site is licensed under a Creative Commons Attribution 4.0 International License.