Increasing the cost accuracy of implementing green retrofitting in high-rise office buildings

Bernadette Detty Kussumardianadewi, Yusuf Latief, Tommy Ilyas, Ayomi Dita Rarasati

Article ID: 3779
Vol 8, Issue 5, 2024

VIEWS - 321 (Abstract) 229 (PDF)

Abstract


Implementing green retrofitting can save 50–90% of energy use in buildings built worldwide. Government policies in several developed countries have begun to increase the implementation of green retrofitting buildings in those countries, which must rise by up to 2.5% of the lifespan of buildings by 2030. By 2050, it is hoped that more than 85% of all buildings will have been retrofitted. The high costs of implementing green retrofitting amounting to 20% of the total initial construction costs, as well as the uncertainty of costs due to cost overruns are one of the main problems in achieving the implementation target in 2050. Therefore, increasing the accuracy of the costs of implementing green retrofitting is the best solution to overcome this. This research is limited to analyzing the factors that influence increasing the accuracy of green retrofitting costs based on WBS, BIM, and Information Systems. The results show that there are 10 factors affecting the cost accuracy of retrofitting or customizing high-rise office buildings, namely Energy Use Efficiency, Water Use Efficiency, Use of Environmentally Friendly Materials, Maintenance of Green Building Performance during the Use Period, Initial Survey, Project Information Documents, Cost Estimation Process, Resources, Legal, and Quantity Extraction applied. These factors are shown to increase the accuracy of green retrofitting costs.


Keywords


green retrofitting; high rise office buildings; cost accuracy; critical success factors; SEM-PLS

Full Text:

PDF


References


Arshad, M. F., Thaheem, M. J., Nasir, A. R., & Malik, M. S. A. (2019). Contractual Risks of Building Information Modeling: Toward a Standardized Legal Framework for Design-Bid-Build Projects. Journal of Construction Engineering and Management, 145(4). https://doi.org/10.1061/(asce)co.1943-7862.0001617

Ballard G., Pennanen A. (2013). Conceptual Estimating and Target Costing. In: Proceedings IGLC-21, July 2013; Fortaleza, Brazil.

Birol F. (2021). Net Zero by 2050: A Roadmap for the Global Energy Sector. International Energy Agency 2021.

Birol F. (2022). World Energy Outlook 2022. International Energy Agency 2022.

Brokbals, S., Wapelhorst, V., & Čadež, I. (2019). Calculation of risk costs in construction projects. Civil Engineering Design, 1(3–4), 120–128. Portico. https://doi.org/10.1002/cend.201900014

Bylund C., and Magnusson A. (2011). Model-Based Cost Estimations—An International Comparison. Division of Construction Management.

Castro, S. S., Suárez López, M. J., Menéndez, D. G., & Marigorta, E. B. (2019). Decision matrix methodology for retrofitting techniques of existing buildings. Journal of Cleaner Production, 240, 118153. https://doi.org/10.1016/j.jclepro.2019.118153

Chin, W. W. (1998). The partial least squares approach to structural equation modeling. Modern methods for business research, 295(2), 295–336.

El-Sayegh, S. M. (2008). Risk assessment and allocation in the UAE construction industry. International Journal of Project Management, 26(4), 431–438. https://doi.org/10.1016/j.ijproman.2007.07.004

Fan, Y., Ren, M., Zhang, J., Wang, N., & Zhang, C. (2022). Risk identification and assessment on green product certification — Model construction and empirical analysis. Journal of Cleaner Production, 370, 133593. https://doi.org/10.1016/j.jclepro.2022.133593

Green Building Council Indonesia. (2016). Greenship Existing Building Version 1.1. Green Building Council Indonesia. JUNI.

Hair, J. F., Hult, G. T. M., Ringle, C. M., Sarstedt, M., Danks, N. P., & Ray, S. (2021). Partial Least Squares Structural Equation Modeling (PLS-SEM) Using R. In Classroom Companion: Business. Springer International Publishing. https://doi.org/10.1007/978-3-030-80519-7

Hair, J. F., Hult, G. T. M., Ringle, C. M., Sarstedt, M., Danks, N. P., & Ray, S. (2021). Partial Least Squares Structural Equation Modeling (PLS-SEM) Using R. In Classroom Companion: Business. Springer International Publishing. https://doi.org/10.1007/978-3-030-80519-7

Halpin D.W., and Woodhead R.W. (1998). Construction Management. Wiley.

Handayaniputri A., Riantini L.S., Latief Y., and Dwiantoro D. (2019). Development of e-maintenance in green building maintenance and repair work of government buildings based on work breakdown structure using building information modeling. International Journal of Engineering Research and Technology, 12(12).

Hidayah, D. N., Latief, Y., & Riantini, L. S. (2018). Development of work breakdown structure standard based on risk for safety planning on dam construction work. IOP Conference Series: Materials Science and Engineering, 420, 012003. https://doi.org/10.1088/1757-899x/420/1/012003

Hudoyo, C. P., Latief, Y., & Sagita, L. (2019). Development of WBS (Work Breakdown Structure) Risk Based Standard for Planning Cost Estimation at Port Project. IOP Conference Series: Earth and Environmental Science, 258, 012051. https://doi.org/10.1088/1755-1315/258/1/012051

Husin A.E., and Priyawan P. (2023). Implementation of the Last Indonesian Minister Regulation of 2022 uses SEM-PLS and Blockchain-BIM to Green Cost efficiency. Journal of Sustainable Architecture and Civil Engineering, 32(2).

Husin, A. E., Ardiansyah, M. K., Kussumardianadewi, B. D., & Kurniawan, I. (2023). A Study on the Application of Green Retrofitting in the Ready-Mix Concrete (RMC) Industry in Indonesia to Improve Cost Retrofitting Performance. Civil Engineering and Architecture, 11(5A), 2958–2973. https://doi.org/10.13189/cea.2023.110812

Husin, A. E., Prawina, R. S., Priyawan, P., Pangestu, R., Kussumardianadewi, B. D., Sinaga, L., & Kristiyanto, K. (2023). Optimizing Time Performance in implementing Green Retrofitting on High-Rise Residential by using System Dynamics and M-PERT. Civil Engineering Journal, 9(12), 3060–3074. https://doi.org/10.28991/cej-2023-09-12-07

Husin, A. E., Priyawan, P., Kussumardianadewi, B. D., Pangestu, R., Prawina, R. S., Kristiyanto, K., & Arif, E. J. (2023). Renewable Energy Approach with Indonesian Regulation Guide Uses Blockchain-BIM to Green Cost Performance. Civil Engineering Journal, 9(10), 2486–2502. https://doi.org/10.28991/cej-2023-09-10-09

Husin, A. E., Sihombing, S. A., Kussumardianadewi, B. D., & Rahmawati, D. I. (2020). Improving The Cost Performance of Mechanical Electrical and Plumbing (MEP) Works Buildings In Hotel Based on Building Information Modeling (BIM) 5D. CSID Journal of Infrastructure Development, 3(2), 228. https://doi.org/10.32783/csid-jid.v3i2.168

Jessup L., Valacich J. (2003). InformationSystem Today. New Jersey.

Laudon K.C., and Laudon J.P. (2014). Management Information Systems Managing the Digital Firm Thirteenth Edition. Pearson Education Limited.

Leni S.R., Yusuf L., Budi S., and Miralia R. (2017). Development of Risk-Based Standardized WBS (Work Breakdown Structure) For Cost Estimation of Apartment’s Project. University of Indonesia. pp 822–833.

Lestari D, and Waryanto N.H. (2012). Indikator User Satisfaction Dalam Layanan E-Learning. In Seminar Nasional Matematika dan Pendidikan Matematika (pp. 978–979).

Marchewka J. T. (2015). Information Technology Project Management, 5th edition. Northern Illinois University. John Wiley & Sons, Inc.

Martoyo W.U., Suprapto F. (2010). Usability and utility evaluation study (Indonesian). Web. SESINDO.

Mitchell, M., & Pulvino, T. (2001). Characteristics of Risk and Return in Risk Arbitrage. The Journal of Finance, 56(6), 2135–2175. Portico. https://doi.org/10.1111/0022-1082.00401

Olatunji O.A. (2011). A Preliminary Review On The Legal Implications of BIM and Model Ownership. Journal of Information Technology in Construction, 16.

Pasichnyi, O., Levihn, F., Shahrokni, H., Wallin, J., & Kordas, O. (2019). Data-driven strategic planning of building energy retrofitting: The case of Stockholm. Journal of Cleaner Production, 233, 546–560. https://doi.org/10.1016/j.jclepro.2019.05.373

Persons T.M. (2020). Cost Estimating and Assessment Guide. The U. S. Government Accountability Office (GAO).

Project Management Institute. (2017). A Guide to the Project management body of knowledge.

Rossi G., Pastor O., Schwabe D., and Olsina L. (2008). Web Engineering: Modelling and Implementing Web Applications. Human-Computer Interaction Series.

Serpell A.F. (2005). Improving Conceptual Cost Estimating Performance. AACE International Transactions; Morgantown.

Takahashi, K., & Liang, E. (1997). Analysis and design of Web-based information systems. Computer Networks and ISDN Systems, 29(8–13), 1167–1180. https://doi.org/10.1016/s0169-7552(97)00040-8

The Institute of Risk Management (IRM). (2002). A Risk Management Standard. Available online: https://www.theirm.org/media/4709/arms_2002_irm.pdf (accessed on 1 November 2001).

The Ministry of PUPR-RI. (2018). Training of Risk Management dan Leadership. BPSDM The Ministry of PUPR-RI.

The Ministry of PUPR-RI. (2021). Regulation No. 21 of 2021. The Ministry of PUPR-RI. Available online: https://jdih.pu.go.id/internal/assets/plugins/pdfjs/web/viewer.html?file=https://jdih.pu.go.id/internal/assets/assets/produk_parsial/PermenPUPR/2021/03/PermenPUPR21_part_1.pdf (accessed on 1 April 2021).

The Ministry of PUPR-RI. (2022). Circular Letter of the Minister of Public Works and Public Housing Number 01/SE/M/2022 of 2022 concerning Technical Guidelines for Green Building Performance Assessment (Indonesian). The Ministry of PUPR-RI.

Thurairajah N., and Goucher D. (2013). Advantages and Challenges of Using BIM: A Cost Consultant’s Perspective. In: 49th ASC Annual International Conference Proceedings.

Wallace, L., & Keil, M. (2004). Software project risks and their effect on outcomes. Communications of the ACM, 47(4), 68–73. https://doi.org/10.1145/975817.975819

Wardahni N. I. (2019). Structural Equation Model of the Relationship between Policies, Work Breakdown Structure (WBS), Guidelines, Information Systems, and Building Information Modeling (BIM) on Maintenance Performance in Tall Buildings (Indonesian). In Tesis (Issue 1) 2019. (Paynter & Pearson).

Watchson D., and Latief Y. (2019). Development of Information System for Building Maintenance of Rented Housing Based on Work Breakdown Structure (WBS) with Building Information Modeling (BIM). ASIA International Multidisciplinary Conference.

Xie, X., Lu, Y., & Gou, Z. (2017). Green Building Pro-Environment Behaviors: Are Green Users Also Green Buyers? Sustainability, 9(10), 1703. https://doi.org/10.3390/su9101703

Zou, P. X. W., Zhang, G., & Wang, J. (2007). Understanding the key risks in construction projects in China. International Journal of Project Management, 25(6), 601–614. https://doi.org/10.1016/j.ijproman.2007.03.001




DOI: https://doi.org/10.24294/jipd.v8i5.3779

Refbacks

  • There are currently no refbacks.


Copyright (c) 2024 Bernadette Detty Kussumardianadewi, Yusuf Latief, Tommy Ilyas, Ayomi Dita Rarasati

License URL: https://creativecommons.org/licenses/by/4.0/

This site is licensed under a Creative Commons Attribution 4.0 International License.